Scaffold calculator
Bays = each elevation length Γ· the bay length, rounded up. Lifts = platform height Γ· 2 m, rounded up. Standards = 2 Γ (bays + 1) per run. Modular face braces go in each end bay and every third bay. A 12 m run at 6 m in 2.4 m modular bays is 5 bays plus a ladder bay, 3 lifts and 14 standards.
Your job
System
Kwikstage-style modular scaffold: standards, ledgers and transoms that lock together, with steel planks.
Elevations
Each run is counted as its own straight scaffold, with ends at both sides.
Bays and platform
Default from Waco Kwikform's Kwikstage guidelines (written under AS/NZS 1576.3 and AS/NZS 4576): unless the scaffold is designed otherwise, a diagonal face brace in each end bay and every third bay, at every lift, and a lateral brace at each end.
Base
One under every standard, each sitting centrally on a sole board. Adjustable base jacks (screw jacks) level the scaffold on uneven ground; start at the highest point with the least extension.
Platforms, edges and access
Guardrails sit 900 to 1100 mm above the platform with a midrail halfway (at least 950 mm in the UK). Ladder bays get a landing at every lift, and each ladder reaches at least 900 mm above the platform it serves.
UK: build to a TG20 compliance sheet or the manufacturer's guide, or have it designed by calculation by a competent person, and erect it with scaffolders competent for that structure.
Estimate only. The scaffold design, ties, bracing and loads are for a competent person or engineer, following the system's instructions.
The first run in elevation: standards, lifts, the decked platform with its guardrails, braces and ties, and the ladder bay.
Bays
6bays
3 lifts high, 1 ladder bay included
Lifts
3
2.0 m apart, top lift decked
Standards
14posts
7 m each to the top rail
Planks
40
5 across, 1.2 m wide bays
Ties
4
Every second standard, 4 m up
Braces
15
Face braces in bays 1, 4, 6 of run 1, plus lateral braces at the ends
| Component | Size | Qty |
|---|---|---|
| Standards | 3 m | |
| Standards | 1 m | |
| Ledgers (each lift, both faces) | 2.4 m | |
| Guardrail and midrail ledgers | 2.4 m | |
| Transoms | 1.2 m | |
| End guardrail and midrail transoms | 1.2 m | |
| Steel planks | 2.4 m | |
| Toe boards | 2.4 m | |
| End toe boards | 1.2 m | |
| Face braces (one per lift in each braced bay) | 2.4 m bay | |
| Lateral braces (both ends, every lift) | 1.2 m wide bay | |
| Adjustable base jacks (screw jacks) | one per standard | |
| Sole boards | ||
| Ladders (one per lift in each access bay) | at least 2.9 m long | |
| Ties | every second standard |
Type over any quantity to match your yard or system. Edits go into the copied list, job sheet, print, share link and email.
The working, with your numbers
- 1. Bays12.00 Γ· 2.40 β + 1 ladder= 6
- 2. Lifts6.00 Γ· 2.0, rounded up= 3
- 3. Standards2 Γ (bays + 1) per run, each 6.00 + 1.00 m= 14
- 4. Planksbays Γ 5 Γ decked lifts, plus ladder landings= 40
- 5. Bracesface: end bays and every 3rd bay Γ 3 lifts; lateral: 2 ends Γ lifts, per run= 15
- 6. Tiesevery second standard Γ levels at 4 m= 4
Scaffold estimate (metremate.com/calculators/scaffold-calculator)
- Kwikstage-style modular scaffold: 12.00 m long, top platform at 6 m
- 6 bays at 2.4 m Γ 3 lifts, 5 boards wide
- Standards, 3 m: 28
- Standards, 1 m: 14
- Ledgers (each lift, both faces), 2.4 m: 36
- Guardrail and midrail ledgers, 2.4 m: 12
- Transoms, 1.2 m: 21
- End guardrail and midrail transoms, 1.2 m: 4
- Steel planks, 2.4 m: 40
- Toe boards, 2.4 m: 6
- End toe boards, 1.2 m: 2
- Face braces (one per lift in each braced bay), 2.4 m bay: 9
- Lateral braces (both ends, every lift), 1.2 m wide bay: 6
- Adjustable base jacks (screw jacks), one per standard: 14
- Sole boards: 14
- Ladders (one per lift in each access bay), at least 2.9 m long: 3
- Ties, every second standard: 4
- Estimate only. A competent person designs and erects the scaffold; check licences and the system's instructions.
The formula, in plain words
- 1Bays per run = run length Γ· bay length, rounded up, plus any ladder access bays.
- 2Lifts = top platform height Γ· the lift height (2 m), rounded up. Standards = 2 Γ (bays + 1) per run, each as long as the platform height plus the top rail.
- 3Modular: ledgers on both faces at every lift, transoms at every pair of standards and lift, planks across every decked bay, guardrail and midrail ledgers and toe boards on the open face and ends.
- 4Tube and coupler: tube for standards, ledgers and guardrails in stock lengths, putlogs at the board span, boards that span whole bays, couplers by type, and a brace in the end bays with at most four unbraced bays between.
- 5Modular bracing, from Kwikstage guidelines written under AS/NZS 1576.3 and AS/NZS 4576: a diagonal face brace in each end bay and every third bay at every lift, and a lateral brace at each end of every lift.
- 6Ties: modular at every second standard every 4 m up; tube and coupler at most 4.8 m (and two bays) apart and 4.2 m up. An adjustable base jack (screw jack) or a base plate on a sole board under every standard.
- 7Every quantity in the component list can be typed over; the calculated number stays alongside, and your edits go into the copied list, job sheet, print, share link and email.
Worked example
A 12 m elevation with the top platform at 6 m, in Kwikstage-style modular scaffold with 2.4 m bays, 5-plank (1200 mm) transoms, the top lift decked and one ladder access bay.
- 1.Bays: 12 Γ· 2.4 = 5, plus 1 ladder bay = 6. Lifts: 6 Γ· 2 = 3.
- 2.Standards: 2 Γ (6 + 1) = 14, each 6 + 1.0 m = 7 m (two 3 m and one 1 m).
- 3.Ledgers: 2 faces Γ 6 bays Γ 3 lifts = 36, plus 12 guardrail and midrail ledgers on the top lift. Transoms: 7 Γ 3 = 21.
- 4.Planks: 6 bays Γ 5 planks on the top lift = 30, plus 10 for the ladder bay landings = 40.
- 5.Ties: every second standard (4 columns) at the 4 m level = 4.
- 6.Braces: the end bays and every third bay are bays 1, 4 and 6, so 3 Γ 3 lifts = 9 face braces, plus a lateral brace at both ends of each lift = 6. 15 braces in all.
- 7.Screw jacks: one under each standard = 14, each on a sole board (14).
Answer: 6 bays, 3 lifts, 14 standards, 36 ledgers, 40 planks, 15 braces, 14 screw jacks and 4 ties.
How to measure it
- Measure each elevation along the building face off the floor or site plan, including returns and set-backs.
- Measure the height from the ground to where the top working platform needs to be, off the elevations.
- Check the gap between the scaffold and the wall: over 225 mm (300 mm in New Zealand) the inner face needs guardrails too.
- Take the bay length, lift height, tie and brace pattern from the system's instructions or the scaffold design, and change the defaults to match.
Where the numbers come from
Every default in the calculator is a number a supplier or manufacturer publishes. We list the source next to it so you can check.
| What | Value | Source |
|---|---|---|
| Unless designed otherwise, diagonal braces on the outside face at each end bay and every third bay, and laterally at each end of the scaffold; bracing is installed at each new lift | 3 bays (brace every third bay) | Waco Kwikform, Guidelines for safe use of scaffold: Wedgelok / Kwikstage scaffold (given under AS/NZS 1576.3 clause 1.6 and AS/NZS 4576 clause 10.3.3) (checked 2026-10-07) |
| Adjustable baseplates (jacks) under all standards, placed centrally on soleplates; a set is 2 jacks for 2 standards | 1 per standard | Waco Kwikform, Guidelines for safe use of scaffold: Wedgelok / Kwikstage scaffold (given under AS/NZS 1576.3 clause 1.6 and AS/NZS 4576 clause 10.3.3) (checked 2026-10-07) |
| Modular ledgers (bay lengths) sold: 700, 1200, 1800 and 2400 mm | 2.4 m longest | Skelscaff (Australian scaffold supplier), product pages (checked 2026-10-07) |
| Modular transoms: 480 mm (2 boards), 700 mm (3 boards), 1200 mm (5 boards) | 1.2 m (5 boards) | Skelscaff (Australian scaffold supplier), product pages (checked 2026-10-07) |
| Modular standards sold in 3, 2.5, 2, 1.5, 1 and 0.5 m lengths | 3 m longest | Skelscaff (Australian scaffold supplier), product pages (checked 2026-10-07) |
| Steel planks 225 mm wide, in 0.7, 1.2, 1.8 and 2.4 m lengths to match the bays | 225 mm wide | Skelscaff (Australian scaffold supplier), product pages (checked 2026-10-07) |
| Fully planked platforms nominally 2 m apart vertically | 2 m | SafeWork NSW, Erecting, altering and dismantling scaffolding Part 1: Prefabricated steel modular scaffolding (checked 2026-10-07) |
| Tie every second standard at 4 m (maximum) vertical intervals; first row no more than 4 m above the ground | 4 m max | SafeWork NSW, Erecting, altering and dismantling scaffolding Part 1: Prefabricated steel modular scaffolding (checked 2026-10-07) |
| That tie pattern assumes at most 20 m high, bays up to about 2.4 Γ 1.3 m and 10 planked levels; beyond it, an engineer's analysis | 20 m max height | SafeWork NSW, Erecting, altering and dismantling scaffolding Part 1: Prefabricated steel modular scaffolding (checked 2026-10-07) |
| Ladders in a separate ladder access bay wherever space permits | 1 separate ladder access bay | Safe Work Australia, General guide for scaffolds and scaffolding work (checked 2026-10-07) |
| Ladder top at least 900 mm above the highest platform it serves | 900 mm | SafeWork NSW, Erecting, altering and dismantling scaffolding Part 1: Prefabricated steel modular scaffolding (checked 2026-10-07) |
| Guardrail 900 to 1100 mm above the working surface, with mid-rails and toe-boards | 900 to 1100 mm | SafeWork NSW, Code of Practice: Managing the risk of falls at workplaces (2019) (checked 2026-10-07) |
| Guardrails 900 to 1100 mm high, midrail halfway; edge protection on open sides and ends; toeboards on all platforms | 900 to 1100 mm | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
| Top guard-rail at least 950 mm; no unprotected gap over 470 mm; suitable toe-boards | 950 mm minimum | Work at Height Regulations 2005 (UK), Schedule 2 (checked 2026-10-07) |
| Guardrails on the inner face where the scaffold is more than 225 mm from the working face | 225 mm | SafeWork NSW, Erecting, altering and dismantling scaffolding Part 1: Prefabricated steel modular scaffolding (checked 2026-10-07) |
| Full edge protection where the gap to the working face exceeds 300 mm | 300 mm | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
| Duty classes: light 225 kg per bay, about 450 mm wide; medium 450 kg, about 900 mm; heavy 675 kg, at least 1000 mm | 450 mm (light) | Safe Work Australia, General guide for scaffolds and scaffolding work (checked 2026-10-07) |
| Baseplate under every standard; soleboards at least 38 mm thick and 200 Γ 500 mm on soft ground | 500 Γ 200 Γ 38 mm | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
| Scaffold tube 48.3 mm outside diameter, 4 mm wall (BS EN 39) | 48.3 mm | Scaffolding Direct, galvanised scaffold tube 48.3 mm x 4 mm (BS EN 39) (checked 2026-10-07) |
| Tube stock lengths 21, 18, 16, 13, 10, 8, 6, 5 and 4 ft | 21 ft longest | George Roberts (scaffold tube, board and fittings supplier), product listing (checked 2026-10-07) |
| Timber scaffold boards 225 mm wide, 38 mm thick | 225 mm Γ 38 mm | BSI, BS 2482 Specification for timber scaffold boards (checked 2026-10-07) |
| Boards stocked in 3.9, 3.0, 2.5, 1.8, 1.5, 1.2 and 0.9 m lengths | 3.9 m longest | George Roberts (scaffold tube, board and fittings supplier), product listing (checked 2026-10-07) |
| 38 mm boards supported at centres up to 1.2 m, or 1.5 m for the machine-graded grade | 1.2 m (1.5 m machine graded) | BSI, BS 2482 Specification for timber scaffold boards (checked 2026-10-07) |
| Boards overhang their support by at least 50 mm and no more than four times their thickness | 50 mm min, 4 Γ thickness max | HSE (UK), Scaffolding: general information (checked 2026-10-07) |
| Tube and coupler: max bay length 2.4 / 2.4 / 1.8 m, bay width 1.575 / 1.275 / 1.275 m, putlogs for timber planks 1.4 / 1.2 / 0.9 m (light / medium / heavy) | 2.4 m bay (light, medium) | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
| Maximum lift height 2.0 m (2.5 m allowed at the first lift) | 2 m max | NASC TG20 operational guide slides (2024), published on Sell2Wales (checked 2026-10-07) |
| Lift spacing between working lifts 1.8 to 2.1 m | 1.8 to 2.1 m | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
| Longitudinal bracing at about 45Β°: brace end bays of every run, at most four unbraced bays; swivel couplers to standards | 4 unbraced bays max | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
| Ties at most 4.8 m apart horizontally (and two bays) and 4.2 m vertically, on two standards or ledgers with right-angle couplers; first level no higher than three times the base width or 4.2 m | 4.2 m vertical | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
| Ledgers to standards with right-angle couplers, putlogs to ledgers with single couplers, sleeve joiners end to end, a putlog within 300 mm of each pair of standards | 300 mm (putlog from each pair of standards) | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
| Max working platforms in one bay: light 4 / medium 2 / heavy 2 up to 13.5 m; 2 / 1 / 1 up to 33 m | 4 light duty working platforms (to 13.5 m) | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
| Scaffolding work from which a person or object could fall more than 4 m needs a scaffolding high risk work licence (basic class covers modular scaffolds) | 4 m | Safe Work Australia, General guide for scaffolds and scaffolding work (checked 2026-10-07) |
| Erecting scaffolding any part of which is 5 m or more above the ground needs a certificate of competence; erecting or dismantling scaffolding a person may fall 5 m or more from is notifiable work | 5 m | Health and Safety in Employment Regulations 1995 (NZ), regulations 2 and 53 (checked 2026-10-07) |
| Give WorkSafe 24 hours' notice of particular hazardous work | 24 hours | WorkSafe New Zealand, Particular hazardous work (notifications) (checked 2026-10-07) |
| Unless built to a recognised standard configuration (such as a TG20 compliance sheet), a scaffold must be designed by calculation by a competent person | 2 routes: TG20 configuration or a design | HSE (UK), Scaffolding: general information (checked 2026-10-07) |
| Tube and coupler scaffolds over 33 m high must be designed by a chartered professional engineer (CPEng) | 33 m | WorkSafe New Zealand, Good Practice Guidelines: Scaffolding in New Zealand (2016) (checked 2026-10-07) |
Manufacturers named here are the source of the number, not a recommendation. Confirm quantities with your supplier.
Frequently asked questions
Stop typing measurements in by hand
MetreMate measures every wall, floor and roof straight off your PDF plan. Then it hands you the same numbers this calculator asks for.
Try MetreMate freeEstimate only. Check quantities and stocked sizes with your supplier. Free calculators at metremate.com/calculators.